| Effective: 6/28/12 |
The Generator Interconnection-Small Business Practice provides the procedures and requirements for Small Generator Interconnection (SGI).
Version 3 incorporates the Suspension of Linked Transmission and Generation Requests Bulletin in Section H.
| Phone: | (360) 619-6047 |
| Email: | Interconnection@bpa.gov |
| Overnight Delivery Service |
Bonneville Power Administration Transmission
Required Phone Number: (360) 619 - 6080 The address above should be used if the Interconnection Customer requests a return receipt. |
| US Postal Service |
Regular Mail Only – Express or return receipt requested mail must be sent to the address shown under Overnight Delivery above. Bonneville Power AdministrationTransmission Marketing and Sales - TSE-TPP-2, P.O. Box 61409, Vancouver, WA 98666-1409 |
|
Address emailed Interconnection Requests to: Important: Enter “Generator Interconnection” as the Subject Line of the email
|
|
| Facsimile (fax) |
A cover page specifying the number of Interconnection Requests and the number of pages should accompany Interconnection Requests submitted by fax. Faxed Interconnection Requests will be accepted only at (360) 619-6940 BPA Transmission Services is not responsible for the failure of fax transmissions. |
• Generator Interconnection-Large
• Generator Interconnection- Small
• Long-Term Firm Queue Management
• Network Open Season Bulletin 2008
• Network Open Season Bulletin 2009
• Network Open Season Bulletin 2010
| Version 3 | 6/28/12, Version 3 incorporates the Suspension of Linked Transmission and Generation Requests Bulletin in Section H. |
| Version 2 |
10/01/09 Version 2 of this Business Practice includes a new section delineating the eligibility criteria to determine whether the Generating Facility is subject to the Small Generator Interconnection Procedures (SGIP). The eligibility criteria may be found in section 3 of this Business Practice. This Business Practice also includes the following changes:
|
| Version 1 | 04/08/08 This is a new Business Practice derived from the Small Generator Interconnection Procedures, Attachment E in the OATT describing the process under which Customers submit an application for interconnection of a generation facility with maximum output capacity not to exceed 20 MW as described under the Federal Energy Regulatory Commission’s (FERC) Order 2006. |
BPA Transmission Services Business Practices - Compiled 5/13/2013